Data CenterAI InfrastructureTexas$642M Capital StackTier III+

Lone Star Compute Campus:
Tier 1 Data Center Underwriting

A 36–72 MW AI-ready wholesale and colocation campus in the South DFW growth corridor — underwritten with institutional discipline, phased capital deployment, and zero speculative assumptions.

$642M
Total Development Cost
12.9–16.4%
Levered IRR Range
15.2%
LP Net IRR
2.15–2.95X
Equity Multiple

The Underwriting Thesis

The DFW data center market holds 869.5 MW of existing inventory with 425.1 MW under construction — 78% of which is already preleased. ERCOT has 239 GW of large-load interconnection requests pending. The market is not speculative. It is structurally undersupplied in a region where power is available, taxes are favorable, and hyperscale demand is accelerating.

The Lone Star Compute Campus is a 52-acre, 300,000 SF gross development targeting 36 MW of critical IT load in Phase 1, expandable to 72 MW ultimate capacity. The campus is designed as a Tier III+ concurrently maintainable facility with an 8 MW direct liquid cooling hall for AI workloads and standard rack densities of 8–15 kW/rack for traditional enterprise tenants.

What separates this underwrite from the market noise is discipline. Power-first, not land-first. Contracted megawatts, not occupancy rates. Milestone-based capital deployment, not speculative construction. This is how institutional capital underwrites data centers — and it is the standard Bonica Capital applies to every engagement.

What Creates Value. What Destroys It.

"This is not occupancy. This is contracted megawatts."

Value Creators

Contracted MW — the only metric that matters
Bankable utility path — secured pre-close
Long-dated take-or-pay — lease floors
AI-ready liquid cooling — flexibility
Phased build — capital follows conviction
Institutional operating discipline

Value Destroyers

Energization delays — the silent IRR killer
Stranded capacity — at 50% utilization doubles effective cost
Soft LOIs — treated as bankable commitments
Overstated PUE — in a hot climate
Under-reserved — battery, generator, and cooling lifecycle
Assuming a premium exit — without proving why

Campus Specifications

A Tier III+ AI-ready campus built for the next decade. 52 acres. 300,000 SF gross. 140,000 SF white space. Dual-feed utility target with one-line verified. The AI zone in Phase 1 is an 8 MW direct liquid cooling hall capable of 50–80+ kW/rack — purpose-built for the GPU clusters that hyperscale and enterprise AI tenants require.

Gross Site52 AcresInitial Campus36 MW Critical IT Load
Expansion Capacity72 MW UltimateGross Building Size300,000 SF
White Space~140,000 SFTier TargetTier III+ / Concurrently Maintainable
Utility FeedsDual-Feed (one-line verified)RedundancyN+1 Mechanical · Robust Electrical
AI Zone (Phase 1)8 MW Direct Liquid CoolingStandard Rack Density8–15 kW/rack
AI Hall Rack Density50–80+ kW/rackCooling StrategyHigh-Efficiency Air + DLC Zone

Capital Follows Conviction — Not Speculation

Three disciplined phases. No blind speculative spend.

Phase 1
12 MW
$258M
Prove It
Trigger
Land + utility path secured + anchor pipeline established
Purpose
Prove energization. Prove market entry. Prove the thesis.
Phase 2
12 MW
$196M
Scale It
Trigger
70%+ of Phase 1 contracted MW achieved
Purpose
Scale with visibility, not hope.
Phase 3
12 MW
$188M
Complete It
Trigger
75%+ Phase 2 contracted MW + utility readiness confirmed
Purpose
Complete the initial campus with full institutional backing.

$642M — Every Dollar Accounted For

~$17.8/W blended — Tier III+ AI-ready, Texas market-calibrated

Cost Bucket$MM
Land Acquisition$18.2M
Sitework / Entitlement / Civil$32.0M
Utility Upgrades / Feeders / Substation$74.0M
Shell and Core$105.0M
Electrical Plant$158.0M
Mechanical / Cooling Plant$122.0M
Network / Security / DCIM / BMS$24.0M
Soft Costs / Design / Legal / Permits$31.0M
Contingency$28.0M
IDC / Financing / Reserves$30.0M
Green-Tech Package$20.0M
Total$642.2M

A $642M Stack Built for Institutional Confidence

Source$MM%
Senior Construction Loan$385.3M60.0%
C-PACE / Green Assessment$51.4M8.0%
GP / LP Common Equity$205.5M32.0%
Total$642.2M100.0%

Debt Assumptions

Senior Loan Term36 months + extension options
Refi Target DSCR1.30x+
Refi Target LTV~60%
RecourseBurns down after stabilization tests

C-PACE Note: Attractive green financing — requires first-mortgage lender consent given its senior lien position. Verified pre-close.

The Promote Is Earned — Not Assumed

LP Returns

Invested Capital$174.7M
Total Return (Yr 10)$436.8M
2.50X
Net Multiple
15.2%
Net IRR

GP Returns

Invested Capital$30.8M
Total Return (Yr 10)$117.0M
3.80X
Net Multiple
21.5%
Net IRR
"The GP only achieves outsized returns if the LP achieves exceptional returns. The alignment is absolute."

Stress Tests & Downside Cases

We don't just model success. We model failure.

Utility Delay (12 Months)

Impact

Interest during construction (IDC) increases. Project-level IRR drops by ~180 bps.

Mitigant

Milestone funding prevents major capital deployment until the utility path is contractually cleared and long-lead items are secured.

Lease-Up Stalls (50% Occ.)

Impact

DSCR drops to ~1.05x. Equity distributions halt. Effective cost per watt spikes.

Mitigant

Phased build architecture. We do not commence construction on Phase 2 until Phase 1 is 70%+ leased.

OpEx Blowout (+20%)

Impact

Stabilized NOI drops by ~$4.6M. Implied exit value drops by ~$70M.

Mitigant

Power costs (40–60% of OpEx) are passed through to tenants. Maintenance and security contracts are locked pre-energization.

Technology Obsolescence

Impact

Liquid cooling becomes mandatory for all new deployments; air-cooled infrastructure becomes obsolete.

Mitigant

Slab-on-grade design supports 350+ lbs/sqft. Chilled water loops are pre-sized and routed to support direct-to-chip cooling retrofits.

Why Bonica Capital for Data Center Underwriting

Most real estate advisory firms treat data centers like office buildings with better tenants. They underwrite occupancy instead of contracted megawatts. They model PUE as a footnote instead of a deal-defining variable. They ignore energization timelines — the single most common IRR killer in data center development.

Bonica Capital brings institutional-grade underwriting discipline to data center development: power-path analysis, utility interconnection risk modeling, contracted MW ramp schedules, AI-density premium capture, and phased capital deployment structures that protect LP capital at every milestone. The Lone Star Compute Campus underwrite is a demonstration of that capability — applied to a real site, with real market data, and zero heroic assumptions.

If you are developing, acquiring, or capitalizing a data center asset and need underwriting that will withstand institutional scrutiny — this is the work we do.

Full Underwriting Memorandum

Review the complete 21-page institutional underwriting package below.

Open Full Screen ↗Download PDF

Submit Your Data Center Deal

Working on a data center acquisition, development, or recapitalization? Submit your deal for a confidential review.